top of page

Comprehensive On-Site Hydrogen Production OPEX and CAPEX Analysis (100 Nm³/hour)

Updated: Aug 18

Green Hydrogen Production Project
Green Hydrogen Production Project

Note: The following data is based on preliminary estimates from Hovogen's equipment. Specific figures may vary depending on project requirements and actual conditions.


1. System Specifications and Operational Parameters

Electrolyzer System Design

· Technology: Proton Exchange Membrane (PEM) Electrolyzer

· Capacity: 100 Nm³/hour (nominal), derated to 90 Nm³/hour for lifespan optimization

· Daily Output: 2,000 Nm³ (20 operational hours/day)

· System Efficiency: 55 kWh/kg H₂ (4.94 kWh/Nm³)

· Stack Design Lifespan: 30,000 hours (extendable to 35,000 hours at 80% load)

· Balance of Plant (BOP) Lifespan: 15 years (no replacement required within 10-year horizon)

Key Operational Assumptions

Parameter

Value

Rationale

Annual Operating Days

350 days

15 days/year allocated for maintenance, system checks, and unforeseen downtime

Daily Operational Hours

20 hours

Avoids peak electricity tariffs; aligns with solar generation profile

Solar Electricity Cost

0 RMB/kWh

Fully integrated on-site PV system; no grid dependency

Bottled Hydrogen Cost

9.90 RMB/Nm³

Based on 40 RMB/bottle (4.54 Nm³/bottle) + 11% waste adjustment



2. Capital Expenditure (CAPEX) Breakdown

Initial System Investment (Year 0): 6,000,000 RMB

Component

Cost (RMB)

Share

Technical Details

PEM Electrolyzer Stack

3,500,000

58.3%

Includes membrane electrode assemblies (MEAs), bipolar plates, and assembly labor

Balance of Plant (BOP)

1,800,000

30.0%

Covers purification units, cooling systems, transformers, and control software

Installation & Commissioning

700,000

11.7%

Civil works, electrical integration, safety certification, and operator training

Stack Replacement Schedule

· First Replacement (Year 4.3): 3,500,000 RMB (after 30,000 operational hours)

· Second Replacement (Year 8.6): 3,500,000 RMB (after 60,000 hours)

· Partial Replacement (Year 8.6): 1,166,667 RMBCalculation:Cost=(10,000 hr/30,000 hr)×3,500,000=1,166,667 RMB

(Required for final 10,000 hours of operation)

Total CAPEX (10 Years)

Component

Cost (RMB)

Timing

Initial System

6,000,000

Year 0

Stack Replacements

8,166,667

Years 4.3 & 8.6

Total

14,166,667

 



3. Operating Expenditure (OPEX) Analysis

Annual Fixed Costs

Component

Cost (RMB/year)

Breakdown

Depreciation

1,416,667

Straight-line method over 10 years (14,166,667 ÷ 10)

Maintenance

220,000

 

  • Preventive

80,000

Quarterly servicing: membrane integrity checks, seal replacements

  • Predictive

88,300

AI-driven monitoring (vibration sensors, gas purity analyzers)

  • Consumables

51,700

Filters, demineralized water, coolant fluids

Labor

120,000

0.5 FTE technician (200 RMB/hour × 600 hours/year)

Total Annual OPEX

1,436,667

 

Variable Costs

· Electricity: 0 RMB/kWh (solar-powered)

· Water: 0.05 RMB/Nm³ → 35,000 RMB/year (integrated into consumables)

Unit Production Cost Calculation

· Daily OPEX: 1,436,667/350=4,105 RMB/day

· Daily H₂ Output: 2,000 Nm³

· Cost per Nm³: 4,105/2,000=2.05 RMB



4. Bottled Hydrogen Cost Structure

Adjusted Daily Requirement: 2,247 Nm³

(Accounts for 11% waste during handling and storage)

Cost Factor

Calculation

Value

Bottles Required

2,247/4.54

495 bottles/day

Daily Cost

495×40495×40

19,800 RMB

Annual Cost

19,800×35019,800×350

6,930,000 RMB

Effective Cost/Nm³

19,800/2,247

9.90 RMB



5. Financial Viability Assessment

Payback Period

· Initial Investment: 6,000,000 RMB (Year 0)

· Annual Savings: 6,930,000−1,436,667=5,493,333

· Payback: 6,000,000/5,493,333≈1.09 years

10-Year Net Present Value (NPV)

Discount Rate

NPV Formula

NPV (RMB)

5%

∑Net Cash Flowt/∑(1+0.05)t

36,824,000

8%

∑Net Cash Flowt/∑(1+0.08)t

32,167,000

10%

∑Net Cash Flowt/∑(1+0.10)t

29,331,000

Detailed 10-Year Cash Flow (RMB)

Year

Capital Outflow

Operational Savings

Net Cash Flow

Cumulative Cash Flow

0

(6,000,000)

(6,000,000)

(6,000,000)

1

+5,493,333

+5,493,333

(506,667)

2

+5,493,333

+5,493,333

+4,986,666

3

+5,493,333

+5,493,333

+10,480,000

4

(3,500,000)

+5,493,333

+1,993,333

+12,473,333

5

+5,493,333

+5,493,333

+17,966,666

6

+5,493,333

+5,493,333

+23,460,000

7

+5,493,333

+5,493,333

+28,953,333

8

(4,666,667)

+5,493,333

+826,666

+29,780,000

9

+5,493,333

+5,493,333

+35,273,333

10

+5,493,333

+5,493,333

+40,766,666



6. Sensitivity Analysis

Impact on Cost per Nm³

Parameter

Baseline

Adverse Scenario (+10%)

Cost/Nm³

Change

Stack Lifespan

30,000 hr

27,000 hr

2.28 RMB

+11.2%

Stack Cost

3,500,000 RMB

3,850,000 RMB

2.25 RMB

+9.8%

Electricity Cost

0 RMB/kWh

0.30 RMB/kWh

2.35 RMB

+14.6%

Operating Days/Year

350 days

315 days

2.28 RMB

+11.2%

Break-Even Thresholds

· Maximum Stack Cost: 8,500,000 RMB (143% increase from baseline) before cost exceeds bottled hydrogen.

· Electricity Cost Limit: 1.05 RMB/kWh (at which electrolysis cost = 9.90 RMB/Nm³).



7. Environmental and Sustainability Impact

· CO₂ Emissions Reduction:

· Bottled H₂ Emissions: 10.5 kg CO₂/kg H₂ (SMR + compression)

· Annual H₂ Production: 255,500 kg (2,000×350×0.08992,000×350×0.0899)

· Annual CO₂ Avoided: 255,500×10.5=2,682,750 kg255,500×10.5=2,682,750 kg (2,683 tonnes)

· Equivalent Environmental Benefits:

· Annual sequestration equivalent to 122,000 mature trees.

· Removal of 583 gasoline-powered cars from roads.



8. Risk Management Framework

Technical Risk Mitigation

Risk

Probability

Mitigation Strategy

Stack Degradation

Medium

Operate at 80–90% load; deploy real-time voltage monitoring; negotiate 35,000-hour warranty

Solar Intermittency

High

Install 1.5 MWh battery storage (≈1.2M RMB); secure backup power purchase agreement

BOP Failure

Low

Maintain critical spares inventory; implement semi-annual thermal imaging inspections

Financial Risk Controls

· Stack Price Volatility: Fixed-price contracts with annual escalation caps (max 3%).

· Demand Fluctuation: Hybrid supply model – maintain bottled backup for 5% of daily demand (100 Nm³/day).



9. Implementation Roadmap

Phase

Timeline

Key Activities

Budget Allocation

Procurement

2025-Q3

Finalize stack supplier contract; order BOP components

1,000,000 RMB

Installation

2025-Q4

Civil works completion; system integration; safety validation

700,000 RMB

Commissioning

2026-Q1

Performance testing (ISO 22734); operator training; AI maintenance system setup

300,000 RMB

Optimization

2026-Q2

Ramp-up to 90% capacity; predictive maintenance calibration

150,000 RMB



10. Strategic Recommendations

1. Lifespan Optimization:

· Operate stacks at 80% nominal load (80 Nm³/hour) to extend lifespan to 35,000 hours, eliminating partial replacement needs.

2. Cost Reduction Levers:

· Bulk Procurement: Secure 15% discount for multi-stack orders (e.g., commit to 3 stacks).

· Maintenance AI: Invest 168,300 RMB/year in machine learning tools to reduce unscheduled downtime by 40%.

3. Policy Alignment:

· Leverage provincial green hydrogen subsidies (up to 20% CAPEX support).



Conclusion

Solar-powered hydrogen production at 2.05 RMB/Nm³ (with stack cost of 3.5M RMB) remains highly viable, delivering 79.3% cost savings versus bottled hydrogen. The project achieves breakeven in 13 months and generates 40.8 million RMB net savings over 10 years. Technical and financial risks are fully mitigable through operational discipline and strategic procurement.Stack Replacement Cost: 3,500,000 RMB per 30,000 Operating Hours



1. System Specifications and Operational Parameters

Electrolyzer System Design

· Technology: Proton Exchange Membrane (PEM) Electrolyzer

· Capacity: 100 Nm³/hour (nominal), derated to 90 Nm³/hour for lifespan optimization

· Daily Output: 2,000 Nm³ (20 operational hours/day)

· System Efficiency: 55 kWh/kg H₂ (4.94 kWh/Nm³)

· Stack Design Lifespan: 30,000 hours (extendable to 35,000 hours at 80% load)

· Balance of Plant (BOP) Lifespan: 15 years (no replacement required within 10-year horizon)

Key Operational Assumptions

Parameter

Value

Rationale

Annual Operating Days

350 days

15 days/year allocated for maintenance, system checks, and unforeseen downtime

Daily Operational Hours

20 hours

Avoids peak electricity tariffs; aligns with solar generation profile

Solar Electricity Cost

0 RMB/kWh

Fully integrated on-site PV system; no grid dependency

Bottled Hydrogen Cost

9.90 RMB/Nm³

Based on 40 RMB/bottle (4.54 Nm³/bottle) + 11% waste adjustment



2. Capital Expenditure (CAPEX) Breakdown

Initial System Investment (Year 0): 6,000,000 RMB

Component

Cost (RMB)

Share

Technical Details

PEM Electrolyzer Stack

3,500,000

58.3%

Includes membrane electrode assemblies (MEAs), bipolar plates, and assembly labor

Balance of Plant (BOP)

1,800,000

30.0%

Covers purification units, cooling systems, transformers, and control software

Installation & Commissioning

700,000

11.7%

Civil works, electrical integration, safety certification, and operator training

Stack Replacement Schedule

· First Replacement (Year 4.3): 3,500,000 RMB (after 30,000 operational hours)

· Second Replacement (Year 8.6): 3,500,000 RMB (after 60,000 hours)

· Partial Replacement (Year 8.6): 1,166,667 RMBCalculation:Cost=(10,000 hr/30,000 hr)×3,500,000=1,166,667 RMB

(Required for final 10,000 hours of operation)

Total CAPEX (10 Years)

Component

Cost (RMB)

Timing

Initial System

6,000,000

Year 0

Stack Replacements

8,166,667

Years 4.3 & 8.6

Total

14,166,667

 



3. Operating Expenditure (OPEX) Analysis

Annual Fixed Costs

Component

Cost (RMB/year)

Breakdown

Depreciation

1,416,667

Straight-line method over 10 years (14,166,667 ÷ 10)

Maintenance

220,000

 

  • Preventive

80,000

Quarterly servicing: membrane integrity checks, seal replacements

  • Predictive

88,300

AI-driven monitoring (vibration sensors, gas purity analyzers)

  • Consumables

51,700

Filters, demineralized water, coolant fluids

Labor

120,000

0.5 FTE technician (200 RMB/hour × 600 hours/year)

Total Annual OPEX

1,436,667

 

Variable Costs

· Electricity: 0 RMB/kWh (solar-powered)

· Water: 0.05 RMB/Nm³ → 35,000 RMB/year (integrated into consumables)

Unit Production Cost Calculation

· Daily OPEX: 1,436,667/350=4,105 RMB/day

· Daily H₂ Output: 2,000 Nm³

· Cost per Nm³: 4,105/2,000=2.05 RMB



4. Bottled Hydrogen Cost Structure

Adjusted Daily Requirement: 2,247 Nm³

(Accounts for 11% waste during handling and storage)

Cost Factor

Calculation

Value

Bottles Required

2,247/4.54

495 bottles/day

Daily Cost

495×40495×40

19,800 RMB

Annual Cost

19,800×35019,800×350

6,930,000 RMB

Effective Cost/Nm³

19,800/2,247

9.90 RMB



5. Financial Viability Assessment

Payback Period

· Initial Investment: 6,000,000 RMB (Year 0)

· Annual Savings: 6,930,000−1,436,667=5,493,333

· Payback: 6,000,000/5,493,333≈1.09 years

10-Year Net Present Value (NPV)

Discount Rate

NPV Formula

NPV (RMB)

5%

∑Net Cash Flowt/∑(1+0.05)t

36,824,000

8%

∑Net Cash Flowt/∑(1+0.08)t

32,167,000

10%

∑Net Cash Flowt/∑(1+0.10)t

29,331,000

Detailed 10-Year Cash Flow (RMB)

Year

Capital Outflow

Operational Savings

Net Cash Flow

Cumulative Cash Flow

0

(6,000,000)

(6,000,000)

(6,000,000)

1

+5,493,333

+5,493,333

(506,667)

2

+5,493,333

+5,493,333

+4,986,666

3

+5,493,333

+5,493,333

+10,480,000

4

(3,500,000)

+5,493,333

+1,993,333

+12,473,333

5

+5,493,333

+5,493,333

+17,966,666

6

+5,493,333

+5,493,333

+23,460,000

7

+5,493,333

+5,493,333

+28,953,333

8

(4,666,667)

+5,493,333

+826,666

+29,780,000

9

+5,493,333

+5,493,333

+35,273,333

10

+5,493,333

+5,493,333

+40,766,666



6. Sensitivity Analysis

Impact on Cost per Nm³

Parameter

Baseline

Adverse Scenario (+10%)

Cost/Nm³

Change

Stack Lifespan

30,000 hr

27,000 hr

2.28 RMB

+11.2%

Stack Cost

3,500,000 RMB

3,850,000 RMB

2.25 RMB

+9.8%

Electricity Cost

0 RMB/kWh

0.30 RMB/kWh

2.35 RMB

+14.6%

Operating Days/Year

350 days

315 days

2.28 RMB

+11.2%

Break-Even Thresholds

· Maximum Stack Cost: 8,500,000 RMB (143% increase from baseline) before cost exceeds bottled hydrogen.

· Electricity Cost Limit: 1.05 RMB/kWh (at which electrolysis cost = 9.90 RMB/Nm³).



7. Environmental and Sustainability Impact

· CO₂ Emissions Reduction:

· Bottled H₂ Emissions: 10.5 kg CO₂/kg H₂ (SMR + compression)

· Annual H₂ Production: 255,500 kg (2,000×350×0.08992,000×350×0.0899)

· Annual CO₂ Avoided: 255,500×10.5=2,682,750 kg255,500×10.5=2,682,750 kg (2,683 tonnes)

· Equivalent Environmental Benefits:

· Annual sequestration equivalent to 122,000 mature trees.

· Removal of 583 gasoline-powered cars from roads.



8. Risk Management Framework

Technical Risk Mitigation

Risk

Probability

Mitigation Strategy

Stack Degradation

Medium

Operate at 80–90% load; deploy real-time voltage monitoring; negotiate 35,000-hour warranty

Solar Intermittency

High

Install 1.5 MWh battery storage (≈1.2M RMB); secure backup power purchase agreement

BOP Failure

Low

Maintain critical spares inventory; implement semi-annual thermal imaging inspections

Financial Risk Controls

· Stack Price Volatility: Fixed-price contracts with annual escalation caps (max 3%).

· Demand Fluctuation: Hybrid supply model – maintain bottled backup for 5% of daily demand (100 Nm³/day).



9. Implementation Roadmap

Phase

Timeline

Key Activities

Budget Allocation

Procurement

2025-Q3

Finalize stack supplier contract; order BOP components

1,000,000 RMB

Installation

2025-Q4

Civil works completion; system integration; safety validation

700,000 RMB

Commissioning

2026-Q1

Performance testing (ISO 22734); operator training; AI maintenance system setup

300,000 RMB

Optimization

2026-Q2

Ramp-up to 90% capacity; predictive maintenance calibration

150,000 RMB



10. Strategic Recommendations

1. Lifespan Optimization:

· Operate stacks at 80% nominal load (80 Nm³/hour) to extend lifespan to 35,000 hours, eliminating partial replacement needs.

2. Cost Reduction Levers:

· Bulk Procurement: Secure 15% discount for multi-stack orders (e.g., commit to 3 stacks).

· Maintenance AI: Invest 168,300 RMB/year in machine learning tools to reduce unscheduled downtime by 40%.

3. Policy Alignment:

· Leverage provincial green hydrogen subsidies (up to 20% CAPEX support).



Conclusion

Solar-powered hydrogen production at 2.05 RMB/Nm³ (with stack cost of 3.5M RMB) remains highly viable, delivering 79.3% cost savings versus bottled hydrogen. The project achieves breakeven in 13 months and generates 40.8 million RMB net savings over 10 years. Technical and financial risks are fully mitigable through operational discipline and strategic procurement.

 
 
 

Comments


HOVOGEN (Headquarter)

Dongguan, China

Floor 4, Room 411, No. 10, Keji 2nd Road, Zhongke Innovation Plaza, Songshan Lake High-Tech Industrial Development Zone, Dongguan City, Guangdong, China 523000
Tel/WhatsApp: +86-15916927868 Email: sales@hovogen.com

HOVOGEN (Manufacture Base) Zhuzhou, China

Add:Unit 1208, Building C1, Xinma Jingu Phase III, No. 266 Xinma South Road, Majiahe Street, Tianyuan District, Zhuzhou City, Hunan

HOVOGEN (Office)

HongKong, China

Add:Unit 18, 10/F

Fortune Commercial Building

362 Sha Tsui Road

Tsuen Wan 

Hong Kong

Tel: +852-8402 1602

HOVOGEN (Japan Branch)

Tokyo, Japan

東京都八王子市長沼町104-2ヒルサイドテラス1-4

bottom of page